Key tunnel of China-Laos railway drilled through: constructor

    Source: Xinhua| 2020-04-29 13:34:25|Editor: huaxia

    LAOS-VIENTIANE-CHINA-RAILWAY-COMPLETION

    Engineers of China Railway No. 5 Engineering Group (CREC-5) pose for a group photo to celebrate the completion of the China-Laos railway Ban Konlouang Tunnel in the Namor District of Oudomxay Province, Laos, April 29, 2020. The 9,020-meter Ban Konlouang Tunnel, in the Namor District of Oudomxay Province, some 400 km north of the Lao capital Vientiane, goes through harsh geological conditions, which making its construction a key bottleneck project of the railway. The China-Laos Railway is a strategic docking project between the China-proposed Belt and Road Initiative and Laos' strategy to convert from a landlocked country to a land-linked hub. (CREC-5/Handout via Xinhua)

    VIENTIANE, April 29 (Xinhua) -- China Railway No. 5 Engineering Group (CREC-5) told Xinhua on Wednesday that it has drilled through the Ban Konlouang Tunnel, a key bottleneck project of the China-Laos railway, 43 days ahead of schedule.

    After the completion of the third longest tunnel of the railway, the CREC-5 has bored all its 10 tunnels, out of the total 75 of the railway in northern Laos, and has basically finished its offline engineering work.

    The 9,020-meter Ban Konlouang Tunnel, in the Namor District of Oudomxay Province, some 400 km north of the Lao capital Vientiane, goes through harsh geological conditions of faults, underground rivers, high temperature, water inrush and mud, which makes its construction a key bottleneck project of the railway.

    Since the start of the tunnel construction in March 2017, the CREC-5 has strengthened scientific study to develop multiple advanced engineering techniques and methods.

    With the COVID-19 epidemic setting in, the Chinese engineering company also comprehensively implemented epidemic prevention and control measures during the construction.

    The China-Laos Railway is a strategic docking project between the China-proposed Belt and Road Initiative and Laos' strategy to convert from a land-locked country to a land-linked hub.

    The 414.332-km railway, with 198-km tunnels and 62-km bridges, will run from Boten border gate in northern Laos, bordering China, to Vientiane with an operating speed of 160 km per hour.

    The electrified passenger and cargo railway is built with the full application of Chinese management and technical standards.

    The project started in December 2016 and is scheduled to be completed and open to traffic in December 2021.

       1 2 Next  

    KEY WORDS:
    EXPLORE XINHUANET
    010020070750000000000000011100001390177501
    主站蜘蛛池模板: 中国人xxxxx69免费视频 | 欧美成人在线视频| 四虎影视永久在线观看| 一进一出动态图| 小说区综合区首页| 久久婷婷成人综合色| 欧美日韩国产精品| 免费看的黄色大片| 视频二区好吊色永久视频| 国产精品国产三级国产AV主播| 人妻无码αv中文字幕久久琪琪布| 黄在线观看www免费看| 国内精品久久人妻无码不卡| 中文字幕无码中文字幕有码| 看成年女人免费午夜视频| 国产女人18毛片水真多18精品| 99久久99这里只有免费费精品| 成年男女免费视频网站| 五月综合色婷婷| 毛片a级毛片免费观看品善网| 午夜精品久久久久蜜桃| 麻豆一二三四区乱码| 国产精品高清在线观看93| 一个人免费视频观看在线www| 日本电车强视频在线播放| 亚洲欧美国产精品专区久久| 精品国产v无码大片在线观看 | 国产精品无码免费视频二三区| 久久成人无码国产免费播放| 欧美激情一区二区三区成人| 免费无遮挡无码永久在线观看视频| 青春草国产成人精品久久| 国产精品免费综合一区视频| A级毛片成人网站免费看| 成人在线视频免费| 久久精品免费一区二区| 欧美大香线蕉线伊人久久| 亚洲视频中文字幕在线| 精品久久人人妻人人做精品| 国产三级精品三级在专区| 国产亚洲成归v人片在线观看|